How do I configure so that only one person is assigned to a epic?

I'm currently planning Epics in Portfolio. 

We've estimated an epic to take 15 days

When Portfolio automatically schedules it sets the start / end date to be Nov 8/ Nov 19.

 

I expected the scheduler to slot 3 weeks of time. Nov 8 -> Nov 29 (as it doesn't include weekends)

I believe that it's assigning 11 days because it's assignign two people to work on it. How can I set it up so that automatically, only one person is assigned to an epic?

1 answer

1 accepted

0 votes
Answer accepted
Thomas Atlassian Team Nov 09, 2017

Hi @Vincent Huang,

This is currently not supported, I've created a feature suggestion here: https://jira.atlassian.com/browse/JPOSERVER-2034

I'd encourage you to vote and explain your use case on it in the comments!

As a workaround, you would currently have to manually assign the epic to a single team member.

Cheers,

The Portfolio for Jira Team