Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,557,802
Community Members
 
Community Events
184
Community Groups

How do I associate a Team with a Board in Portfolio for JIRA?

I have created a Plan in Portfolio which contains multiple Projects (lets say A,B,C,D,E and F) and have created two scrum Boards which cover one or more projects (e.g. Board1 covers A,B,C and Board2 covers D,E,F). I then created two teams (Team1, Team2) and I want to associate the teams with the respective boards.

When I go to set up the teams in Portfolio there is a drop-down that says "No associated projects or boards". However, when I click on the drop-down it only offers me a list of Projects but not boards, and it only allows the selection of one project.

How can I associate my teams to boards, rather than being forced to have one team per project?

 

1 answer

1 vote
Rik de Valk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Jun 05, 2018

Hi Carl, To link boards to teams you must add the Boards as Issue Source. So it is not sufficient to have the projects as Issue Sources. The reason is that some data (sprints, velocity) is linked to Boards, not projects. So have you added the Boards as issue sources in you Plan Configuration? 

Thank you, Rik! That solved my issue.