You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
I have created a Plan in Portfolio which contains multiple Projects (lets say A,B,C,D,E and F) and have created two scrum Boards which cover one or more projects (e.g. Board1 covers A,B,C and Board2 covers D,E,F). I then created two teams (Team1, Team2) and I want to associate the teams with the respective boards.
When I go to set up the teams in Portfolio there is a drop-down that says "No associated projects or boards". However, when I click on the drop-down it only offers me a list of Projects but not boards, and it only allows the selection of one project.
How can I associate my teams to boards, rather than being forced to have one team per project?
Hi Carl, To link boards to teams you must add the Boards as Issue Source. So it is not sufficient to have the projects as Issue Sources. The reason is that some data (sprints, velocity) is linked to Boards, not projects. So have you added the Boards as issue sources in you Plan Configuration?