How can I use schedule start and end date populated by portfolio ?

Hi 

I would like to use schedule start and end date populated by portfolio plan in a report.

Could you please let me know if this is possible to use outside of portfolio itseld?

 

Thanks

Naama

1 answer

0 votes

Hello,

Target Start and End date are available in the JQL at this time, but not the Schedule Start and End date unfortunatly.

We have the following feature request in place to track interest in this as a new feature:

https://jira.atlassian.com/browse/JPOSERVER-447

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,592 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you