Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Next challenges

Recent achievements

  • Global
  • Personal

Recognition

  • Give kudos
  • Received
  • Given

Leaderboard

  • Global

Trophy case

Kudos (beta program)

Kudos logo

You've been invited into the Kudos (beta program) private group. Chat with others in the program, or give feedback to Atlassian.

View group

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

How can I show Scrum Teams and Kanban Teams in a single plan?

I have one Project with a single backlog. The backlog is split between 2 scrum teams and one kanban team. Will the kanban team need it's own portfolio plan or can it be shown along with the other two scrum teams?

2 answers

2 accepted

0 votes
Answer accepted

Hi Ebony,

It's certainly not necessary to have separate plans for each. You can definitely have multiple teams of different types within the same plan.

However, I would recommend that if each team has a big scope (1000s of open issues being worked on at any time) then it would be worth having separate plans for each.

Let me know if you have any questions about that.

Regards,

Shannon

0 votes
Answer accepted
Ryan Fish Community Leader Aug 02, 2018

@Ebony Burroughs
Two steps:
1. Select your portfolio then select "configure" from the ellipsis next to the portfolio name
Add the teams under configuration/ issue sources.
Select the board to pull issues (kanban, scrum, agile)

2. From your portfolio landing page select team tab
select "create team"
name it then add
find the team from your list and select the issue board to pull issues from (Kanban or Scrum)

Thanks Ryan. I followed these steps but after I "create team" and associate it to the appropriate board, it shows as Scrum. I figured out I had to go into the plan configuration settings and change the Planning unit to days to give me the option to change this team to Kanban.

Ryan Fish Community Leader Aug 06, 2018

You are welcome Ebony, the source is whatever instantiation the board was originally, i.e. if it was created as a Kanban board, then the source will be Kanban. 
Good call on changing it. You found a way! :)

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

6,586 views 25 19
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you