How can I postpone the start date of my plan in Portfolio?

So, I'm planning ahead for the next quarter. Basically, the plan in portfolio needs to start next week, July 2nd.
problem is that we've been customizing Portfolio since one month now, so the start date was one month ago. Until the end of June, we are not using Portfolio to plan, but simply jira. 
How can the future work to get done at a later defined date?

1 answer

You can use "Earliest Start Date" for this. It's a field that, unfortunately, can only be configured in Portfolio for Jira itself.

Yep. That's what I did. For some reason it didn't recalculate properly at first, but then the more I was committing changes, at some point it just got updated with the correct start date. It's a little bit of a struggle to have to put the earliest date for all single epics. Just a simple plan start date would be better, but it worked. Thanks! 

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,248 views 18 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you