You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi all,
we are currently testing the Advanced Roadmaps feature within the Jira Premium subscription. I used the 'Auto-schedule' feature to plan a few dummy tasks with a team of the 'Kanban' team type. After auto-scheduling, many of the tasks obtain the duration of one although some of them have a duration > 1 (see image below) . Is this the expected behavior or a bug?
Kind regards
Alex
Hi,
is this still an issue? How many hours or days have you allocated to the team?
Hi Ollie,
thank you for your reply.
The team has a capacity of 200 hours per week. I think the duration of one on the timeline above is due to the team capacity of 40 per working day. An estimate of 2 days corresponds to 16 hours (due to our global time tracking settings). So the task could be processed in one day by the whole team. However I find this a bit confusing because if a person is assigned to a task I cannot assume that the whole team is working on the task.
I think I would have to generate a team for every assignee such that this works as I expect it to.
Kind regards
Alexander