Doing relative story point to estimate US, can we still do capacity planning

If we are doing relative story point to estimate user stories, can we still use capacity planning.

My understanding is the user stories should be estimated on Ideal days, then you can use the team capacity because you add the hours that each team members is available and that is how the calculation is set.

1 answer

0 votes

Hi Nazee!

Yes, Stories' estimation (story points) are done on a consistent manner, regardless of team capacity. Then based on your Velocity (which you might want to update over time as it gets more precise or changes) Portfolio is able to calculate the date while taking into account other capacity factors like holidays.

Let me know if you have any additional questions. In the meantime, you can review this:

Regards,

Shannon

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

3,528 views 22 15
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you