Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Next challenges

Recent achievements

  • Global
  • Personal

Recognition

  • Give kudos
  • Received
  • Given

Leaderboard

  • Global

Trophy case

Kudos (beta program)

Kudos logo

You've been invited into the Kudos (beta program) private group. Chat with others in the program, or give feedback to Atlassian.

View group

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Does anyone else find the "Dependency scheduling" explanatiion confusing?

Perhaps it's due to being Monday morning, but during a review of my sechduling options, I decided to review the "Dependency Scheduling" section closely.

I can choose to either Rank a dependent item below a required item,  or alternatively, Rank a required item above a dependent item.....

 

So, insofar as these two seem to be exactly the same option, I checked the specific documentation at https://confluence.atlassian.com/jiraportfolioserver/dependencies-schedule-844237026.html.

 

hmmm.  Not enlightening at all, and clearly needs to be re-written --

1 answer

1 accepted

1 vote
Answer accepted

I agree it's confusing, but they don't do the same thing exactly.  Take the example of stories and dependencies from that page you linked.

If Rank dependent work item below required item is selected, it schedules it in the below order, even though it's not ranked that way:

  1. Story 2
  2. Story 3
  3. Story 4
  4. Story 1

So even though Story 1 is the 1st priority, it's scheduled below Story 4 since you said to rank the dependent item (Story 1) below the required item (Story 4).  Since Story 4 is the 4th priority, Story 1 gets scheduled below it, in this case it is scheduled 4th.

If you select Rank required work item above dependent item, it does the opposite, and schedules it in this order:

  1. Story 4
  2. Story 1
  3. Story 2
  4. Story 3

In this case you're saying rank required item (Story 4) above dependent item (Story 1). Since Story 1 is the 1st priority, it schedules Story 4 above it.

Thanks Steven. It would be nice to see your explanation added to or replacing the one provided by Atlassian.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Advanced Roadmaps

3 short videos to help you get started with Advanced Roadmaps

Hi community, I’m Roi, a product manager working on Advanced Roadmaps for Jira. While Advanced Roadmaps is a powerful tool to plan and track work at scale, we know it can be challenging to get star...

6,586 views 25 19
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you