Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

Dependencies mapping not updating portfolio timelines

Carlos Eduardo González June 18, 2018

I've configured the portfolio dependencies in a way that if "Issue A blocks issue B, then Issue A is scheduled before issue B"

 

However, I've set a dependency from "Epic Yellow" to "Epic Red" in a way that:

Yellow is blocked by Red

I would expect for Red to be scheduled before Yellow, however, Yellow is still showing first on the timeline. 

The ranking is updated just fine, but the timeline has not been impacted.

Help please!

 

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events