I've configured the portfolio dependencies in a way that if "Issue A blocks issue B, then Issue A is scheduled before issue B"
However, I've set a dependency from "Epic Yellow" to "Epic Red" in a way that:
Yellow is blocked by Red
I would expect for Red to be scheduled before Yellow, however, Yellow is still showing first on the timeline.
The ranking is updated just fine, but the timeline has not been impacted.
Help please!
Hi everyone, We’re always looking at how to improve Confluence and customer feedback plays an important role in making sure we're investing in the areas that will bring the most value to the most c...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events