Change date when add new issue

Hi,

I have a team that works on development and maintenance.

Possible situation:

 Programmer development -> Production system failure ->Programmer go to maintenance work -> Programmer comes back to development

 

I'd like to add Issue in Jira e.g "System Failure" as "blocks Story" and set duration on e.g 2 days. And i'd like to show delay on roadmap (move end time in Story).

 

It's possible?

 

sorry for my weak language

Thank you

Kobi

0 answers

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Confluence

An update on Confluence Cloud customer feedback – June 2022

Hi everyone, We’re always looking at how to improve Confluence and customer feedback plays an important role in making sure we're investing in the areas that will bring the most value to the most c...

140 views 1 3
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you