Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,556,610
Community Members
 
Community Events
184
Community Groups

Best practice for start/end dates in Advanced Roadmaps

I'm starting to roll out Advanced Roadmaps in our organisation. It's a relatively mature Jira instance so it has a number of custom fields for start/end dates depending on the context.

Are there any best practices for selecting which date fields should be used for start date / end date in Advanced Roadmaps? When I create a brand new plan it defaults to "Start Date" (custom field 12010) and "Due Date" (the in-built field).

How do others have this set up?

Are people tracking planned dates and actual dates separately? I'm thinking that's not very relevant when planning using scaled agile techniques.

3 answers

1 accepted

0 votes
Answer accepted

I'll answer my own question after 16 months of usage.

Best to use Start Date and Due Date. No need for Target/Planned Start and Target/Planned End as any Start Date/Due Date in the future is "target" and any Start Date/Du Date in the past is "actual".

We're a mature instance but just getting started with Advanced Roadmaps.  We are using Planned Start (custom) and Due Date.

0 votes
elizabeth_jones
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 25, 2021

I have custom fields for Target Start, Target End, which is what drives my roadmap gantt chart. I also use start, due date for tracking actuals to plan. 

Hey @elizabeth_jones 

can you share a bit more on your setup? We are trying to do the same but it seems Warnings are not working on such setup. We want to see a warn when Start date is later than Target start date.

@elizabeth_jones - we have some teams that follow the same pattern, but I'm curious why we even need Target Start & Target End - what's the value prop?  What does it help improve in your company?

A Target/Planned Start Date is needed for the Gantt chart, which some people love for sharing as a visualization with Business partners.

Some teams enjoy using the Target/Planned Start Date for managing the backlog - thinking of starting on time helps finish on time, and also helps sort through the clutter of things that don't need to be started until, say, next month.

I forgot about expectation setting with externals.    Definitely need a separate storage for that.  ;)