We are wanting to use the Data Center version of Plans (formerly advanced roadmap planner) to create a schedule from a template schedule and then use Auto Schedule to adjust the dates for the new plan. To test this out I built a simple set of 4 stories. The first three are linked to each other sequentially as dependencies of each other and the last has no dependencies. I then want to be able to change the estimate, run Auto Schedule, and get an updated plan. When I make changes to the estimate some of the time the Auto Schedule works as expected, updating duration and start/end date. But other times it comes back with no changes. I can not find any pattern to when it updates the schedule and when it doesn't. The only field I am changing is the Estimate fields days value.
1. What do I need to do to get the auto schedule to work
2. For the story that has no dependencies what determines when it get scheduled and can I control that.
Thanks