I want to add an additional board/project in Scenario b of my portfolio planning. How can I do that? Reason: I want to separate specific projekt workload from Feature requests and want to show the impact of feature Requests
Thanks in advance
This is not possible - Scenarios are fixed to the plan as you have it configured to boards/projects.
One way to accomplish what you're describing: include the feature requests in your board configuration. Then, associate these workload impacting feature requests to a unique Epic called "Pending Feature Requests" (so they're not at the bottom of the plan) and leave them unestimated and not assigned. Then, in Scenario B you can put estimates on them and see the impact to your schedule and workload.
-Jason Golden
Denver AUG Leader
Hi everyone, We’re always looking at how to improve Confluence and customer feedback plays an important role in making sure we're investing in the areas that will bring the most value to the most c...
Connect with like-minded Atlassian users at free events near you!
Find an eventConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no Community Events near you at the moment.
Host an eventYou're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.