I have created two teams with 11 team members each , I have allocated 29.17 hours /week/team member to all team members which calculates up to 320.8 hours per week.
Now portfolio is showing different capacity for both the teams ( Daily capacity ) for one team it is showing around 80 hours and for another team it is showing 72.9 hours ...so there is an issue in capacity .
Any idea why is this happening ?