Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,558,367
Community Members
 
Community Events
184
Community Groups

Project Advance (Real vs estimated)

Hi everyone

I'd been trying to fin a way to respond a single question: how can i know the % of real advance of my project, vs % of work estimated to be completed, in a specific time, in a project level view.

i tried whit Road maps and Big Gantt Aps, but aren´t very helpfull in this way

Best regards!

2 comments

Marcin Geb _SoftwarePlant_
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
Jul 20, 2020

Hello Gustavo

You can track the progress of a project using the Gantt chart or Scope module (the latter if you're on BigPicture).

Have a look at figure 1, which comes from https://softwareplant.com/tracking-progress-bigpicture-biggantt/ article. The Water supply network project is 52% advanced (the green progress bar). However, at the time the screenshot was taken the project should have been 100% advanced (the blue progress bar) because it was already past the original end date of the project.

The 'Time tracking (Spent)' column is generally better than the 'Time tracking (original)'.

Also, take a look at fig. 2. It shows the better way of tracking progress in the new BigPicture 8, a couple of weeks away from now.

Fig. 1 BigPicture 7

time-spent-remaining-estimate-jira-big-picture.png

 

Fig. 2 BigPicture 8, Overview home screen

bigpicture-8-tracking-progress.png

Rhys Diab _Agile Docs_
Marketplace Partner
Marketplace Partners provide apps and integrations available on the Atlassian Marketplace that extend the power of Atlassian products.
Aug 26, 2020

Hi Gustavo,

I put together an extension called Agile Docs to help with this.

Opens up right inside the project dashboard and gives you a breakdown of how far along your project is in terms of % rolled up estimates completed. Works for time tracking and story point estimates.

estimate-rollup.png

 

Hope that helps!

Best Regards,

Rhys

Comment