Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,552,874
Community Members
 
Community Events
184
Community Groups

Need help on using my project in JIRA Portfolio

I am very new to JIRA and need assistance in using Portfolio for my Project. I am very confused about the following scenarios:

  1. Can a task be dependent on its Epic? When I am doing this, it is saying I am violating the Dependency rule
  2. Should I create a plan with respect to Tasks only?
  3. When I am trying to achieve point number 2, I cannot create a subtask until I click on the master task and create subtasks for the same. With the Portfolio, it gets created as a bug. Is it still considered a Sub task? Please find the attached screenshot.
  4. If you refer the screenshot when you click on AT-44, it doesn't show the linked Bugs which I am assuming should be linked, isn't it? Am I doing something wrong here?
  5. I am allotting time required for completing each task by clicking on each task and entering the data but the same is not reflecting in my Portfolio dashboard.
  6. Added custom fields in my Portfolio tab. The details are reflecting but I cannot put any data into it.  For E.g: I cannot enter any data in the "Man hours" field
  7. How do I plan capacity planning? I have allotted team members for the same for each task. When I check the capacity report, there are no results as shown in the below screenshot. How do I know if a specific resource is overloaded or not

Any help would really be helpful.