count weekends between 2 dates

def countSATSUN=0

if (c2.get(Calendar.DAY_OF_WEEK) == Calendar.SATURDAY|| c2.get(Calendar.DAY_OF_WEEK) == Calendar.SUNDAY)

{

countSATSUN++;

}

this is giving wrong count

Can somebody help

 

1 answer

0 votes

How is the partial snippet you have posted relevant to the question, and how is it connected to atlassian tools?

Such Java/Groovy questions are typically first hit on stackoverflow - https://stackoverflow.com/questions/4600034/calculate-number-of-weekdays-between-two-dates-in-java