Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Greenhopper "Time Remaining" incorrect.

willem odendaal
May 3, 2012

I've seen similar questions to this one, but none answer my question.

When I look at the Greenhopper Planning board, on the right hand side under the current Version it states that only 6h 11m of time has been spent out of 418 hours.

However, when I look left to the tasks, I can clearly see that about 80 hours have been logged when adding up the Time Spent displayed on each card.

Where does Greenhopper get its incorrect time spent calculation from?

UPDATE (Monday 07 May):

When I look at this page now the time spent only shows the hours I logged this morning, completely ignoring the previous time spent as per the previous screenshot. See new screenshot below.

Am I wrong in assuming there is something seriously buggy with how Greenhopper calculates the time spent?

PS: time version start/end date is from 20 March to 25 May.

1 answer

Suggest an answer

Log in or Sign up to answer
0 votes
Ken McClean
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
May 4, 2023

Hello:

Is this for Jira Cloud or Jira Server? The Jira Cloud REST API tends to not return user email addresses, as these are considered private information.

This code returns everything available about the reporter:

 

def issue = get("/rest/agile/1.0/issue/${issue.key}")
.header('Content-Type', 'application/json')
.asObject(Map)
.body


def reporterProperties = issue.fields.reporter

return reporterProperties

 

The email address is not an available property. If you're on Jira Server, it's a different story.

TAGS
AUG Leaders

Atlassian Community Events