Greenhopper "Time Remaining" incorrect.

I've seen similar questions to this one, but none answer my question.

When I look at the Greenhopper Planning board, on the right hand side under the current Version it states that only 6h 11m of time has been spent out of 418 hours.

However, when I look left to the tasks, I can clearly see that about 80 hours have been logged when adding up the Time Spent displayed on each card.

Where does Greenhopper get its incorrect time spent calculation from?

UPDATE (Monday 07 May):

When I look at this page now the time spent only shows the hours I logged this morning, completely ignoring the previous time spent as per the previous screenshot. See new screenshot below.

Am I wrong in assuming there is something seriously buggy with how Greenhopper calculates the time spent?

PS: time version start/end date is from 20 March to 25 May.

2 answers

1 accepted

1 vote
Answer accepted

Why is your start date for version 2 set to none in the gadget? I believe if you hover your mouse over the start date the edit icon should appear. Set your start date and then try refreshing your page. You might need to be an administrator to set date though.

Without a start date, each new day would be like a start date.

Awesome, thanks Norman. That was the problem. Didn't realize that would happen. I set my start date to the actual start date and the time now appears to be calculated correctly.

I would guess that since most of your issues are in open state and only two are in progress state. So time spent are the ones marked in progress.

I've marked them as in-progress. No change unfortunately.

Try logging some time now and see if it shows up or not. I am suspecting older time does not count.

For some unknown reason whenever I log time now, (even on "Open" tasks), the time spent is recorded correctly. So I have *no idea* why the time spent did not have an effect before.

Interesting. What are your start and end dates set to?

My empirical experience has been time was only recorded in the gaget if in-progress state is set and the version is set.

http://confluence.atlassian.com/display/GH058/How+Hour+Burndown+Charts+Relate+to+Time+Tracking+in+JIRA

Please see my update to the question. Time calculation doesn't seem to make any sense at all. I think it's buggy.

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Confluence Cloud

🎨 Add some visual life to your templates

Hi Atlassian Community, My name is Avni Barman, and I am a Product Manager on the Confluence Cloud team. Based on feedback from you, we are giving admins more power to create templates that a...

175 views 2 8
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you