Epic cannot be closed if Story is 'In Progress'

Hello,

I need to find a way to restrict the EPIC from showing the Close transition if the stories in the Epic are in Open or In progress state.

I only have the script runner plugin.

The solution here: http://www.adaptavist.com/w/jira-genius-ensuring-that-epics-are-only-closed-when-stories-are-complete/

Doesn't work as it involves JMWE as well.

 

Thanks a mill.

 

1 answer

1 accepted

1 vote
Accepted answer

Hi miller,

You can have a Simple Scripted Condition with the following script 

import com.atlassian.jira.component.ComponentAccessor

final def LINK_TYPE = "Epic-Story Link"
final def COMPLETE = "Complete"

ComponentAccessor.getIssueLinkManager().getOutwardLinks(issue.id)?.findResults {
it.issueLinkType.name == LINK_TYPE ? it.destinationObject : null
}?.findAll { it.status.statusCategory.name != COMPLETE }?.size() == 0

Hope that helps, Thanos

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Jan 15, 2019 in Statuspage

Introducing Statuspage Getting Started guides! First up: What is Statuspage?

Over the next several weeks we'll be sharing some of our Getting Started guides here in the community. Throughout this series of posts, we'd love to hear from customers and non-customers ab...

270 views 4 2
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you