Hi there
Using the time tracking feature in Jira we have experienced something rather odd. When looking at an Epic and the time tracking field, we would like to see all time logged in all child work items throughout the hierarchy of work items below. At the moment the field only includes the work items and their work logs in the level jus below. This means all work logged on a sub-task level is not included in the time tracking field when looking at it on an Epic level. This leads to misalignment of expected time used on the Epic in total and can lead to misinformation and wrong decisions made if users are not aware of this detail when looking at the time tracking field.
Is there some configuration that needs to be done for it to be able to include work logs from all levels below the current work item?