Ideally, I build this template, including mapping the dependancies and nominal time expected to complete each task. Some a re serial tasks, some are able to be done in parallel.
Within the structure of the template, with dependancies set and nominal time for each, I'm hoping that by setting the last day for the4 last task, everything will adjust backwards showing me when things Ideally should be started. With that insight, I can map the release tasks into our existing sprint cadence.
Is doing this (or even getting close to it) possible? Is the a different/better/easier way to do it?
Cheers.
JGV