Hello everyone !
I'm trying to create, where if I change the start date of an issue for the issue linked, it should change the start date with the same number of days than the parent link.
I figured out a way to create a variable where it calculates the number of days that has change (minus or plus).
Everything is showing correctly in the audit log, if I change the start date for 3 days if show "3", I also have a "SUCCESS" showing, but the start date on the linked issues is being emptied ...

Here is the automation :

And here is the value inside my edit field start date (customfield_id = start date)
{{issue.customfield_10083.plusDays(dateDifference).jiraDate}}
I'm not sure where it blocks and why the field is being emptied ... If anyone has an idea on this !
Thank you !
Have a nice day !