How can I set up a Jira Automation rule to create sub-tasks in reverse chronological order, with due dates calculated backward from the epic's due date?
I'd like to explain the use case for the Automation I want to inquire about.
1. I plan to use it for backward scheduling of the project.
2. Each epic has a different nature. For example, Epic A might be about system development, while Epic B might be about content development.
3. Because of the different development tasks, both Epic A and B need to generate different sub-tasks.
4. Sub-tasks dependent on an epic should have different man-days. For instance, the sequence could be: brainstorming (3 days), idea sketching (1 day), system planning (5 days), and implementation (5 days).