Hi, I have set up 2 automations for auto scheduling a chain of issues (mimicking gantt auto schedule features in similar tools).
The automation rules are:
1. If START DATE is being updated, then DUE DATE is auto calculated and set.
2. If DUE DATE is being updated, then the START DATE of the linked issue (BLOCKS) is auto calculated and set.
So I was hoping that both automation rules will fire each other until it will get to the last issue In the tree, which doesn't have linked issues it BLOCKS. (1 fires 2 which fires 1 and so on)
The problem that the Automation engine stops it after apx. 10 runs with the following error:
-------------
Rule execution was stopped since an execution loop was detected. Please check *all* your rules and disable the 'Allow rule trigger' setting in 'Rule details' where it is not needed. We stopped execution after detecting a long chain of rules triggering other rules. Chain length: 10
-------------
Can you please assist? Many thanks !!