Hi - The screens in a project I supporting currently use the custom field "end date" which is a date picker. The advanced roadmap associated with the board is using "due date" a system field. The project owner asked if the issues could use the "same" due date field type as the advanced roadmap.
1. Would it be okay to remove the due date field from the advanced roadmap configuration and replace with the same end date custom field the issues/screens are using in the project?
2. How do I know "what kind of field" this due date system field is? e.g., is it date/time? is it a date picker type? The project owner wants the issues and road map to have the same due date or end date field types
🫣