Hi
We use Jira cloud as Service Desk and Project management.
So when customers create a Change Request, will we create a linked issue, with the developer tasks. On both the Change Request and the linked issue have we activated the field Due Date.
I have set up so that we automatically updates the Due Date field on the linked issue, if we change it on the customers Change Request. This is working fine.
The problem is that the Developers are seeing the date as "end of date", where the SLA might be the middle of the due date. Therefore do I need to keep one day for Service Desk employees to communicate with the customer.
So I need to subtract one day on the value in the linked issues.
This is the one I have set up where it just align the due date.

Thanks
Bo