hello, we are trying to make a rule that is executed whenever there is a modification in a field of a subtask.
The rule consists of performing an operation on a smart field. In this case, the "progress percentage" field of a task must vary according to the value of the "progress percentage" of its subtasks.
In a scenario of a task with two associated subtasks, the operation should be:
(subtask 1 progress percentage*originalestimate subtask 1+subtask 2 progress percentage*originalestimate subtask 2)/(originalestimate subtask 1+originalestimate subtask 2).
We add a screenshot of the standard as it is, but we still need to complete the additional fields section: