My Epic has the follow structure:
But in the timeline the hierarchy doesn't work:
Timeline works only for sub-tasks.
Hi @Ricardo Otsuka
Epic hierarchical levels do not show on Business (Work Management) Projects at this time, including on the Timeline view.
You can view/vote for the feature request for this - see: JWMCLOUD-111
Ste
Hello @Ricardo Otsuka
Welcome to the community.
Are you working with the Timeline feature in a Business project?
It will say near the top of the left-side navigation pane what type of project it is (Business, Software, etc.) below the project name.
Hello @Trudy P Claspill it's a Business Project.
tks.
I found this post where @John Funk commented in January that Atlassian is aware of that as a change request. I have not found a link to the change request in Atlassian's backlog.
It looks like you're new here. Sign in or register to get started.