I'm having trouble wrapping my brain around this concept on how to do this. I have a list of 7 subtasks that are auto-generated. That's no problem. But my issue is the last 5 subtasks should not be created until the first two are completed. How would I do this?
Hi @Scott Federman and welcome to the community! One approach would be creating two automation rules:
Automation 1: Capture SubTask(s) are complete
Automation 2: Create SubTasks
NOTE - You need the allow rule trigger checkbox to be TRUE
Well said Sir. It worked like a charm.