Hi, I have created an automation rule to send an email alert for the assignee 1day before task due date but its not working as expected.
Please support if you notice any errors in the rule or know any alternative methods.
You can use "due > now() and due <= 1d " in you JQL Condition
In my case, not all field supported by "Issue Field condition" so i solved by add condition in JQL "Document Expiry Date" >= 0d AND "Document Expiry Date" <= 1d, in your case you can add and "due" >= 0d AND "due" <= 1dVahagn Beglaryan.
Hi Pramodya,
We use:
duedate <= startOfDay(1)
Much thanks @John Funk
@Yadi MuchThanks due=1d worked for my scenario.
@Vahagn Beglaryan Much Thanks due=1d worked for my scenario.
Can you click on the Accept Answer? Thanks!
Hi @Pramodya Gamaethige . Could you please explain me the JQL query project = "Group ERP Project Tasks" AND statusCategory !=Done.
I am trying to create a rule to send an email one day before the due date but this is my first time, could you help please.
Thank you