For some reason our setup of Epic Status has Planned below Done. (see image)
What is happening is that upon selecting "Mark as Done" from the Epics panel in the backlog planning view it changes the Epic Status to "Planned" thinking this is the final status step. When going back into the Epic Jira ticket and manually changing this to "Done", the epic shows back up in the Jira Backlog Epics Planning panel.
I used a post function to set the Epic Status to "Done" when the status of the ticket was transitioned to "Done". This does us no good when we go to remove it from the Epic panel in the backlog planning view by "Mark as Done" when this triggers it to transition yet again back to "Planned".
It doesn't help that the field is locked too. If the field wasn't locked, I would just move Planned in between "To Do" and "In Progress" where it probably should be anyway.