Hi - I have 3 teams on a project running 3 parallel sprints. How can I configure/apply the 3 team velocity to the version board such that the board reflects the release date based on the combined velocity? Thanks!
Hi @Gregg Everett
You can't do this out of the box. You will need to extract the data and make some work on excel to aggregate reports from differents teams.
Look at this thread (david almeida answer)
https://community.atlassian.com/t5/Jira-Core-questions/Is-there-a-way-to-aggregate-sprint-reporting-across-multiple/qaq-p/256087
Hi Mohamed - OK, am doing something similar now. appreciate the input.