Hi
There are some posts already on this, but they don't seem to answer my question
https://answers.atlassian.com/questions/8094/where-do-we-enter-story-points
https://answers.atlassian.com/questions/28454/story-points-not-visible-in-create-edit-issue-after-following-greenhopper-101-instructions
So my question - how do i add Story Points
I am in the Agile, Planning Board, i select tools - configuration - Card Styles
Story Points are not available in any of the drop downs (Card view, Summar view etc)
Also - when i create a new User Story, there is no option to add Story Points
Thanks
Ken
Hi Kenneth,
Is it possible that the project or issue type you are working with is not configured to use the story points field?
"When you create a new custom field (see below) you will need to either select the applicable issue type(s) and project(s), or define the custom field to be global."
Double check to make sure the story points field has been made available to the project and/or issue types you are working with. If you don't see the field in the any of the card style configuration options, this is likely the problem.
See configuring a custom field for more on this:
Another thing or two to check is make sure you are using the scrum template for greenhopper. From the planning board go to tools/configuration and verify project template = scrum.
Thanks Adam and David
Indeed, i am using scrum template
Nearly there - extract from second point
It looks like i don't have the authority to Associate the fields (last part)
I need to wait for my Admin person
Having said that - when I click "screens" on the Story Points field, it does seem to be set to "default screen", "workflow screen" and "resolve issue screen"