Greetings,
Kindly Go to Project setting -> Details -> Key
As i know, we can give any characters in Key field which will be merged with indexing number of issue.
For Instance, Key value is CA. So the Issue number will be CA-1, CA-2, etc...
When i try to create sub-tasks, Obviously sub-tasks number will starts with CA-xxx.
Goal Point:
How can i change the Key value as ST instead of CA for sub-task alone. So that, easy way to identify the counting of sub-tasks by the indexing number.
- Parent issue -> CA-xxx
- Sub-task issue -> ST-xxx
Appreciate your kind help.
Thanks
Have a good day.