Hi all.
A lot of my recent work is in hybrid environments so asks from an existing PMO.
The Jira plans work really well and very successful in moving dependency away from MS Project and other static tools.
My question is specifically around Scenario Planning in Plans. While you can create scenarios to discuss a work and timeline change, if you confirm a timeline change, the original timeline becomes lost.
PMOs often ask for current plan versus original, so wondering how people have accommodated this ask ? Is it just a matter of exporting the original and comparing or something else I may be missing ?
Thanks in advance.
Thanks @jeroen.wilmes , the custom field option is also something I have implemented, but finding it a challenge with ongoing date changes. I admit this is likely a process improvement, but was still hoping to find maybe a marketplace app to support.
Hi,
You could log old dates to a custom field and then create another plan that references those dates which you put side by side (if that visual would help :) )
Cheers
Thanks @Clayton , this is also something I have implemented, but finding it a challenge with ongoing date changes.
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Get the most out of Jira
Start with basic Jira terms and navigation. Then, discover how to effectively organize work and customize your Jira experience.
Learning Path
Atlassian tools and practices for developers
Reduce context switching by making Jira more efficient, and apply collaboration best practices for streamlined team operations.
Atlassian Certified Associate
Jira Essentials certification
Validate your knowledge of key Jira concepts like using work items, spaces, boards, and Rovo.