How can I automate moving an idea to a different status once the 'Evaluate Later' date is reached?
You can use Jira Automation to move the idea after a specified date is reached. Here’s how you can set it up:
1. Create a New Automation Rule:
2. Set the Trigger:
3. Add a Condition:
4. Add the Transition Action:
5. Save and Enable the Rule:
Disclaimer: The above should work, but I haven't had the time to test it.
Hi Jens. That was the route that I was attempting with scheduled triggers. The problem is in the JQL query. JPD uses a custom date format that doesn't support that kind of logic. It also isn't a smart value either.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Levi Palmer , you are right. I missed that JPD uses a different format.
After a little bit of research and trial and error I figured out a viable solution.
1. Create variable
Copy a re-formatted JPD value into a variable called targetDate (you can choose a different name). Use the following for the smart value:
{{triggerIssue.customfield_10392.substringAfter("\"end\":\"").substringBefore("\"")}}
2. {{smart values}} condition
Compare the variable to a formatted version of the current date
{{now.jiraDate}} equals {{targetDate}}
That will allow you to check if the JPD date matches today's date.
Hope this helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.