Hello,
Our company has nearly finalized the product development roadmaps for 2026.
I'd like to create a view in JPD that freezes the ideas planning on a specific "presentation day" in 2025. This would allow us to easily compare planned value against earned value.
Is there a feature in JPD that directly supports creating such a "frozen version" of the JPD view, without needing to export it as a JPEG or PDF?
Thanks,
Hi @Lorenzo Giliberti welcome to the Atlassian Community Forums! 👋
Jira Product Discovery (JPD) is focused on idea prioritization and product planning, but it doesn't natively support Earned Value Management (EVM) metrics like Planned Value (PV) and Earned Value (EV) out of the box.
However, you can approximate or manually track PV vs EV in JPD using custom fields and views. Here’s how you could achieve this with a couple of workarounds:
Hello Dave,
thanks for your prompt answer ! Actually we do calculate PV, EV, and AC outside of JPD, it was effectively a non-necessary information I added for justifing my request.
Coming back to the original question, it is not possible to have a "frozen view" without exporting anything ? I do like how easy it is to navigate through a JPD view, and , that why I'm asking.
I do understand that duplicate start date and end date values declared at day d (and respectively copy them in equivalent fields e.g. "planned start date" and "planned end date") might be a potential workaround.
Thanks again :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Lorenzo,
no at the moment you cannot "freeze" the roadmap, the views in JPD otherwise than with export or workarounds.
Regards,
Beata Kupiec
Product Manager @ Jira Product Discovery
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.