I use the the "Delivery Progress" field to report number of Story Points in Delivery issues, and this has now changed to report "99+", when above 98 SPs rather than a precise number - I use the precise number in my reporting to show changes in scope for a Product Discovery Idea, not just a % complete, and it's unnecessarily difficult if e.g. "Done" just reports "99+".

1 answer

1 accepted

0 votes
Answer accepted
Tanguy Crusson
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
December 9, 2025

Hi @John Waymont , I'm checking with the team

Tanguy Crusson
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
December 9, 2025

Update: it's a bug, we'll fix it!

Like John Waymont likes this
Tanguy Crusson
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
December 11, 2025

Ok I had an update from the team and the fix should be rolled out in the next few days