I have a structure with multiple projects which have multiple issue types.
Each of the issue type have assginee name. I want to generate a Gantt chart view with resource levelling.
When I chose option 'Resource Levelling', I 'm not getting any option to chose resources.
I'm getting below message 'Resource Leveling can't be performed. Resources have not been configured or assigned.'.
Appreciate any help here.
Hello @sarathgd ,
In order to use resource leveling, you must first define the value to be used as a resource in the Gantt Configuration.
The linked documentation will outline exactly how to do this.