Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Duration calculation between two dates exclude weekend in confluence?

Godwin jino April 14, 2024

Hi all,

i have created a table macro to calculate number of days between two dates (start date to end date). below i have mentioned the query . could you help me to modify to exclude weekends? 

select *,(CAST(ROUND(ceiling(DATEDIFF(DAY,'Start Date','END Date')))as int))+1+ " days" as 'Duration' from T1

table macro.png


Thanks 

1 answer

1 accepted

0 votes
Answer accepted
Shawn Doyle - ReleaseTEAM
Community Champion
April 16, 2024

You could take the number of days, divide by 7 to get weeks, then multiply by 2 to get the weekends, and then subtract that value from the number of days.  Should get you fairly close.

Some SQL examples can be found here: https://stackoverflow.com/questions/7388420/get-datediff-excluding-weekends-using-sql-server

Godwin jino April 16, 2024


hi Doyle ,
i have updated my query, what are the filed to be modified to complete this table in settings?


 
SELECT
*, 'Days' - 2 * (('Days' / 7)::integer) - CASE WHEN 'Days' % 7 = 0 THEN 0 WHEN 'Start date'::Date->getDay() = 0 THEN 1 WHEN 'Start date'::Date->getDay() + 'Days' % 7 = 7 THEN 1 WHEN 'Start date'::Date->getDay() + 'Days' % 7 > 7 THEN 2 ELSE 0 END AS 'Work days' FROM (SELECT *, ROUND((T1.'End date' - T1.'Start date') / "1d") + 1 AS 'Days' FROM T1)

Godwin jino April 24, 2024

hi @Shawn Doyle - ReleaseTEAM  ,

i have tired above code  working now.

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events