How to set up the connection between tasks

Вероника Арутюнян
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 15, 2021

Situation: when the deadline of one task is postponed, and all other tasks (which connected with it ) are postponed automatically after it

1 comment

Comment

Log in or Sign up to comment
Jack Brickey
Community Champion
November 15, 2021

If you are on Cloud you could use Automation for this. Something like this…

Trigger - due date changed

condition - as required to meet your needs

action - edit linked issue due dates