If I enter 8h for a task estimate it converts and displays as 1d 1h (because available hrs is 7). I just want it always to show hours - 8h.
Thx
Rick
Carlos,
Thx for the reply. Yes that was exactly what I was looking for. Might clarify though that you have to Deactivate the Time Tracking in order to see the screen you presented. Once I figured that out worked like a champ.
Thx
Rick
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Apply agile practices
Transform how you manage your work with agile practices, including kanban and scrum frameworks.
Learning Path
Configure agile boards for Jira projects
Learn how to create and configure agile Jira boards so you can plan, prioritize, and estimate upcoming work.
Jira Essentials with Agile Mindset
Suitable for beginners, this live instructor-led full-day course will set up your whole team to understand how to use Jira with an agile methodology.