Given Jira projects: pA pB where pA has an epic pA.e1 that has story pA.e1.s2 pB has an issue pB.i1 with a remaining estimate of 4w pA.e1.s2 depends on pB.i1 and MyPlan's issue sources =...
Can we have more than 50 teams in advanced road maps or is that the hard limit.
In the advanced roadmaps release view, there is a column titled 'Progress (Issue Count) but the progress bars shown are for story points. Not a big problem but it is confusing to people. ...
Have advanced roadmap loaded with list of issues, as simple as want to sort them in the order of the issue key ( based on which one is created first). however found impossible because it can only sor...
It appears that Epic to be counted as taking par in week has to start before actual week starts. For example in this case it seems that weeks start from Sunday and if I have epic starting on Monday i...
I have an Epic which spans a few fixVersions. In my plan/scenario I am filtering on a single release, 1.12. The issues in the listing have no story points, but the Epic is still showing 3 rolled up p...
I have 3 Epics with the following names: Epic 1 - It has a start date of Jan 1 and End date Jan 31 and Blocks Epic 2 Epic 2 - has no start or end date Blocks Epic 3 Epic 3 - has no start or ...
Hi, I want to create multiple filters and multiple story mapping board with different goals for each story mapping board for a single project. How can I do that? I tried to create multiple filters f...
Hi geeks, I am working on teams available capacity for a time period (3 sprints/6 sprints/PI/mini PI) vis-a-vis Features we receive from PDM. Is there a way we can configure, team wrt their availabi...
Hello Team, I need help regarding my gantt chart view, I want to change colour combination for gantt chart in jira structure and also highlight risk. However not able to find out any option ...
I want display close issue in Program schedule. It seems if I have an Epic with "target start" and "target end" initialized I can see on Program Chart successfully, but when i close the Epic the iss...
Hi I would like some advice regarding the best way to find in which plan(s) is an issue ? In the best case scenario I would have a feature close to what already exist for Agile board "View ...
I've created teams in my ARP Plan using the Existing Team option and now I see that ARP wants to write these teams back to Jira. The teams already existed in Jira so I'm concerned that this will caus...
We have some executive who would not "need" Jira access but would like to see the advance portfolio roadmap. Is there a way to create a URL to see view only without having access to the tools since t...
hello I use Advanced Roadmap and I feel some behaviour issues in the user interface. could you try to improve these? windows 10, Chrome 1. when I clik on the summary of a issue, a popup ap...
The issues assigned to an inactive user are "Unassigned" on Advanced Roadmaps. Step1: I assign an issue to a user Step2: The user leaves the company and his user is disabled. On Advanced Roadmaps ...
I am using Cloud Jira and Confluence. On a Confluence page, I have a table with columns for Capabilities, Epics and Stories. The intent is to show the capabilities, related epics and rela...
Hi, if I create initiatives , do they need to belong to project , or are they above project level and stand alone?
Sorry all, but this might have been a question before. We have different project in our company with each it's own epics. If we create initiatives can you link different epics from different project ...
We have created a roadmap including epics and linked stories. When the roadmap first displays it shows these however all of it disappears as soon as it displays and you are left with no display whate...
In Jira Advanced roadmaps, is there a way to have the plan auto-calculate or set the finish date of a task or story? For example, ID-1: Start date (or target start date) is set to 9/13/2022 and es...
Hi I'm new to Jira Cloud, but used Jira server product in the past. My current department needs a way to visualize/manage in relation to a roadmap epics across multiple teams. in the past...
We are trying to pull the child tickets (Feature) of multiple parent tickets (Initiatives) linked through 'Parent Link' field (advanced roadmaps) without having to do it by issue keys. Example: Lets...
Howdy all... we are eyeballs deep in onboarding our product team (4 product groups of 2-5PMs each) into Jira Software + Advanced Roadmaps. Our engineering teams have been using Jira Software for a wh...
Hi I am using Advanced Roadmaps. I do not see the option to download the view as an image. What am I missing? Thank you.