We have many projects running with Jira. I would like to install and experiment with Portfolio in our production environment, so that I have live, changing project data. Can I install/co...
Hi, we are using JIRA Portfolio and we have a fixVersion 1.0, I have a plan based on that. On top of the items having fixVersion 1.0, the plan will show as well items, which 1. have a blank fixVeri...
If I open up a plan and just hit calculate (without prior changing any target dates or fields) it completely screws up my calculation based on today as start date. How do I revert this?
Hi everyone, I want to configure progress/status tracking options for JIRA Cloud as described here : https://confluence.atlassian.com/jiraportfolioserver/status-and-progress-tracking-715263...
Advanced filter does not have criteria in using Initiatives to filter. Is there a solution?
I use stories --> Epics ---> Version. So a story that is tagged with an epic that is linked to a version should inherit the version at the story level. Shouldn't this be the norm? It app...
...evel ?! That means also that I have Epics without issues assigned from which I know this isn't true, it's only because of the missing issues in portfolio. In the plan I do have all filters cleared and I a...
All the Stories/Tasks not appearing under Epic on Portfolio Plan. I have created a portfolio plan. Desired epics are visible in the plan. But the issue is, for example if an Epic has 10 items(Tasks...
I have created a few plans in portfolio and typically if an epic is unpointed I will have the light blue bar. If the epic has points I will see the dark blue bar. For one particular plan it does not ...
I found this article https://confluence.atlassian.com/jiraportfoliocloud/configuring-working-hours-and-days-828785191.html but don't even know where to find configure? It says: Select yo...
Hello, Is it possible to use only a few licenses for Jira Portfolio and not a license per each user, knowing that we have 23 users, but only 5 users will use Portfolio Thanks.
What if I don't assign an item to a specific person, does portfolio assign it to someone as early as possible where there is some capacity free? And regarding to sprints, does portfolio also a...
After creating a plan in the portfolio getting following error: "There is no scheduled epic in the current result set" While Epics & Stories are appearing under Scope tab.
In portfolio there is 2 fields called scheduled start and scheduled end. How is this configured? I tried to look in my admin settings but these fields are not in the available fields. Is this somethi...
Based on knowledge base articles, the Later release is supposed to start after the last created release date. However, mine is set to start "as early as possible" which is scheduling work concu...
In the Scope panel, issues have a column called "Scheduled start". Unlike "Target start" and "Target end", this does not seem to be editable. Presumably this date is getting pulled from some informat...
Hi everyone This is my first time attempting to create and manage a release. Tried youtube turorials and community boards but can't seem to find an answer Background - I have 3 concurrent sprints ...
Hi, I am looking to incorporate the Portfolio Addon for our cloud instance of JIRA. I was wondering whether the charge per month relates to all active users? Is there a way that we can only pay for...
Hi, We currently have a test plan configured to read a sprint board for a team. There are multiple planning sprints on the board that have started and the next actual sprint is not start...
Hello Portfolians, We are looking to get a deeper understanding on how you prioritize your planned work with Portfolio for Jira. Help us to improve by filling this short survey: https://goo.gl/...
I can include a Kanban board as an issue source when making a plan. However, Epics do not come across. Further, since Kanban stories do not have "size" it seems that the Portfolio is unable to develo...
I have created a Portfolio plan and added in my scope of Epics and then realized that I forgot to add 2 existing JIRA board Epics to the plan. Portfolio allows you to remove from the plan ...
Hi, When I go to the team capacity view, I see that teams/ people / sprints are automatically assigned with items. Is that correct? Or what if I don't assign an item to a specific pers...
In our team, sometimes we ship things between locations. I need the item to reach the destination before I can start working on tasks that involve that item (i.e. waiting for a circuit board to be de...
Hello, I have a few epics that are currently in progress as seen at the scope level in my Portfolio plan. There are a few stories that have been completed for some of these epics, however, I no...