Hi, I am using an advanced roadmap to build a plan. My issues source are Scrum boards. I have created 4 sprints in advance on the board for the team to plan the sprint- I can not set the start and e...
I've been playing around with Advanced Roadmaps and it seems really handy. One issue I'm having with it, though, is that I'm not seeing a way to properly report on the progress of an epic withi...
I have been trying to capacity plan in the new Advanced Roadmaps that replaced Portfolio for Jira and so far I have only been able to get the points vs velocity to show in a 'current sprint' in the r...
We have a custom field that ties into our team database. It is quite a large list. It is a single drop down field. We have to use this field to sort and filter roadmap items by but whenever it is ad...
Hi All Maybe i missed something in the releases, but we upgraded recently and are on Portfolio 3.22 before the upgrade users could commit changes on portfolio into their relevant buckets, after the...
Since basic Roadmaps is only on Next-Gen projects, here are my questions: 1) Is Capacity Planning of some kind available in basic roadmaps? 2) What's the difference between Next-gen projects and Cl...
Hi All, I'm looking for a way to create a report based on Advanced Roadmaps/Portfolio data that could give me a view of team/team member capacity allocation (in story points) t...
This is our current hierarchy with Portfolio Initiative Feature Epic Story SubTask I have a request from a team that doesn't want to use Epics, but link Stories directly to Features. I ...
It is very important to be able to specify a start date on an issue as a fixed constraint when using auto-scheduling. Everyone needs this, I guarantee it. Advanced Roadmaps auto-schedule does not see...
When filtering issues in the new Advanced Roadmaps view, we did not find a way to combine several labels with an AND-relation, but they are usually considered as OR-linked. This makes it tedious to,...
All of my filters using the parent field (which were working last week) are now returning errors that Field 'parent' does not exist or you do not have permission to view it. When I be...
Does Priority & Estimation plays any role when Auto Scheduling feature is enable in advanced roadmap
Let me start by saying that I've been using Jira for years with both scrum and kanban projects for software development. I consider myself fairly competent in its base operation and I am now trying t...
Greetings, I have signed up for a Portfolio virtual class. I was wondering what the best plugs into Jira/Confluence were for project management tracking (cost/schedule/performance) ...
Several days ago, Atlassian introduced Advanced Roadmaps, what they referred to as a major refresh of the product previously called Portfolio for Jira Cloud. I am relatively new to the Portfolio pro...
Program View shows Scheduled Start/End dates for many epics. As far as we can tell, those dates are populated by the Target Start/End dates set in the Plan view for that epic. However, for some sign...
We have been using both Jira and JAMA in our company and in JAMA we were using the concept of multiple "upstreams" This is very important as we can have the same story enabling multiple Epics. We wer...
During the Portfolio 3.0 demo, the sprint info is displayed under the date row. I am not able to configure. Any help is appreciated. Thank you
Hi, I'm evaluating Jira Portfolio so I'm a newbie regarding this product besides being an experienced Jira administrator. My use case of Jira Portfolio is to select only specific Epics and their ta...
Hi - I would like to export all Epics and associated GTMHub OKRs tagged to it. I can see linked OKR (as seen in screenshot) but dont know how do i export this along with Epics. Many Thanks ...
Hi, Our jira instance is enabled with Portfolio add-on and the Portfolio Teams field is configured in the scheme and the scheme is enabled to a project. Now I have created 2 new teams from th...
Hi Experts, I use both Biggant & Portfolio in my organization in following ways: Biggantt -- I use this for my project planning. Link multiple Jira projects and have a Tree structure for ...
I have a license, but it keeps saying trial period has ended, and it doesn't let me enter the license.
Hi All, I am working on calculating a portfolio plan and below is the issues I am facing. Example: I have 5 stories with two fixed versions (Version-1 and version-2 respectively), When I filter th...
| Subject | Author | Posted |
|---|---|---|
| June 3, 2025 7:00 AM PDT | ||
| May 27, 2025 6:28 AM PDT | ||
| May 5, 2025 1:42 PM PDT | ||
| November 13, 2024 5:08 PM PST | ||
| September 12, 2024 1:17 AM PDT |