Hi, Can you delete timelines in the Advanced Roadmap view after it's created? Thanks. Cheers, Vince
Hello, It's noticed that changing Target Start/End dates in a roadmap instead in a Jira ticket breaks their synchronization - as of that moment the dates changed in a ticket don't affect them in a r...
Hi all, Is it possible to group issues on advanced roadmaps by reporter? Thanks and BR Verena
How do I exclude weekends from the timeline view in Advanced Roadmaps? I found old documentation that suggests you can set working hours in the "Configure" menu for your plans, but I don't see the op...
I am creating a plan in Roadmaps. For simplicity, this plan contains 2 Jira projects, 2 team boards (one for each project), 1 epic that contains issues from both projects. When completin...
Hi, I want to list all child issues assigned to a certain team. Is this possible? Is it possible with scriptrunner plugin? As step 2 I want to list parents who has child issues assigned to certain ...
Hi there, Recently we have migrated back to Jira Classic project type (Company Managed). This was due to the lack the ability to use Advanced Roadmaps in combination with Next-Gen project type (I ...
Generally in the early year, team want to know their resource capacity vs their year end roadmap so as to do their annual capacity planning, at such stage, team will only have the hight level require...
We upgraded Jira server to version 8.13.12 and Advanced Roadmaps to version 3.29.8. After this upgrade, our built-in filters are resulting in an error that roadmap fields could not be found. Is ther...
I cannot reach my on cloud Jira
or do you have any other suggestion to use to plan across teams and also plan the teams capacity? thanks, Lea
Hi I try to use the auto-schedule so our Epics "Start date" and "End Date" will be the results of the earliest story allocation and the latest story as it should be for some reason,...
Hi, I am looking for a way to be able to report of historic epics, from longer than 12 months, is this possible? Otherwise i would have to keep epics constantly open so i don't lose historic...
We have added custom start and end dates to our Jira project and kanban board and are able to add the fields to AR dashboard display. However, when we try to use these new dates when configuring the ...
Roll up feature is working in the Jira portfolio plan but while doing review changes it is not getting saved in the particular jira ticket . Please find the attached snapshot. As seen in the below sn...
The Dependencies are configured to be worked on sequentially which means the dependency badges should turn RED if there is a conflict in schedule. BUT that is NOT happening. PLease advise, what am I...
A feature for Advance Roadmaps for Programs is the Sync to keep things up to date. (see attachment) but you have to remember to do this manually. How can I automate it?&...
Hi there, I'm setting up Advanced Roadmaps for TWO projects; with some core members but some floating resources. Is there a way to have Shared Teams have multiple Associated issue sources?&nbs...
Good Morning, We are on Jira Cloud and we have a project with 100s of cards. The board admin wants to be able to use a field when creating the ticket to then have the cards sort themselv...
In our Plan one of the teams seems to be appearing twice, one version has all the expected issues, the duplicate row for this team has only one issue and says "External - Team currently not in this p...
I am trying to create a list of all the all the inititative where the stories have not updated. Therefore i wrote JQL below to limit my search to the stories only that i am interested / were n...
Using Advanced Roadmaps (on Jira DataCenter) - 3.24 (8.13) The badges for dependencies are not turning red even with conflicting timelines with dependent issue. I selected 'Sequential' for dependen...
I am looking to start using the advanced roadmap \ plans (sprint capacity management view) using hours as the measure and estimating tasks in hours and am expecting to get these 2 benef...
Hi, it is not possible to display our team from the Roadmap in our Jira Kanban board. I can create a new task in the roadmap with the team - then it is displayed in the Jira board, but when I want t...
When we created epics from advanced roadmaps. it dint created the epics in real. you can find that epic to associate it with a story. Secondly, we have an initiative and in advanced roadmaps screen ...