My plan in the portfolio with all the task still to-do status. But after some task in completed/done, the task disappears in the plan.
My Portfolio Plan setting:
Estimation: days
Dependencies: Concurrent
Completed issues: 60 days
Planning interface: improved planning interface
Portfolio version: 3.5.0
Solved! Go to Solution.
Hi Steven,
The "completed issues day configuration" is in the "Issue sources" section of the configuration page.
Regards,
Raathi
Hi,
I found the problem. The resolution in completed task is still unresolve.
After add post addition to change the resolution, the completed task is reappear in plan.