Hi,
I created a story and subtasks under the story. My team added task-level story points. Is there a way to automatically calculate the total story points of this story?
Thanks
Solved! Go to Solution.
@Edwin Meijer - hope all is well! Saw your second post to Daniel and that's something we can definitely help with in minware. Let me know if you want to chat!
Hi @Hiti Verma
This can be done in Advanced Roadmaps using the "roll-up" feature! Please try selecting "View Settings" in the top left of your plan, then checking the "Others" box in the "Roll-up" section.
From there, you'll be able to see on your roadmap view the sum of all your sub-task story points rolled up to the story issue I've included a screenshot of what it should look like below - you can see the arrow pointing to the "8" indicates that it's a roll-up value.
Let me know if you have any trouble getting that set up and I'd be happy to help out!
Cheers,
Daniel
If I were to use the "View Settings" and enable groups based on labels... is there a way to roll up the story points to these groups?
Currently, Advanced Roadmaps only rolls up story points to the highest issue type in the hierarchy, but not to groups.
For example, I have labeled some features tickets with a label and configured my View Settings in Advanced Roadmap, and any feature that has a certain label is grouped as "Core Platform":
My current workaround is to export the data and perform the rollup in a spreadsheet, but this is suboptimal...