I have defined my project with 2-week sprint in JIRA but when looking at the plan in Portfolio, Portfolio seems to overwrite this with a 6-week sprint length except for my currently ongoing sprint.
I read the hint to start up all the sprints in JIRA, but that really creates a mess in JIRA to make the plan look nice in Portfolio. Can't I have the best of both worlds?
Hey Flemming,
In your Portfolio setting make sure that it's set up as a Scrum based plan and then you should be able to set up your Sprint length to your desired 2 weeks.
This guide should be able to help: https://confluence.atlassian.com/jiraportfolioserver/scheduling-settings-715263133.html
Hope this helps,
Tyler
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.